A Success Story Insight: Cost Escalation Analysis for Rail and Tunnel Infrastructure
Accura Consulting was engaged to undertake a detailed cost escalation analysis for a major rail and tunnel project that faced significant financial pressures due to disruptions caused by the COVID-19 pandemic.
This analysis aimed to quantify the impact of rising material and labour costs, providing a robust foundation for the project’s claims and ensuring fair resolution with all stakeholders.
Approach to Cost Escalation Analysis
The cost escalation exercise undertaken by Accura Consulting followed a structured, data-driven approach:
Comprehensive Data Collection
Data from project records, invoices, and supplier agreements was gathered and reviewed to understand historical and forecasted costs.
Key cost drivers, including materials (steel, concrete), labour, and equipment, were identified as the key focus of the analysis.
Development of Cost Models
Tailored cost models were created using reliable indices and market data, including national and regional construction cost indices.
International benchmarks were referenced where local data was unavailable or insufficient, ensuring comprehensive coverage of cost categories.
Scenario Analysis
Multiple scenarios were developed to account for varying degrees of escalation:
A baseline scenario reflecting standard market trends.
A moderate scenario incorporating actual inflation rates observed in the construction sector.
A high-impact scenario projecting further escalation based on worst-case market conditions.
Validation of Findings
The cost models were cross-verified with actual data from supplier invoices and historical project expenditures to ensure accuracy.
Independent reviews and expert validation provided further confidence in the findings.
Key Components of the Analysis
Material Costs
Reinforcing Steel: The analysis revealed significant price increases driven by supply chain disruptions and global market volatility. The cost per tonne increased by approximately 33%, reflecting market trends validated against regional indices and supplier data.
Concrete: Ready-mixed concrete costs increased by over 11% due to increased production and transportation expenses. Escalation rates were benchmarked using historical data and confirmed through supplier records.
Labour Costs
Labour costs rose due to restricted workforce availability and increased demand for skilled personnel. The analysis showed an average rate increase of 10.22%, aligned with published wage indices and verified against contractor invoices.
Forecasting Future Escalation
Using construction cost indices and market projections, Accura Consulting developed forecasts to estimate escalation impacts for the remaining project duration.
Indices for critical cost components, such as steel, concrete, and labour, were adjusted based on real-time market trends and future inflation expectations.
Outcomes of the Analysis
Clear Quantification of Escalation
The cost escalation attributable to COVID-19 impacts was quantified, providing a transparent basis for claims.
Each cost category’s contribution to overall escalation was itemized, ensuring clarity and precision in the claims raised.
Support for Claims Resolution
The findings were presented in detailed reports, offering stakeholders a robust framework to address escalation impacts fairly and efficiently.
Informed Decision-Making
The project team used the analysis to guide budget adjustments, allocate resources effectively, and develop mitigation strategies to minimize further cost increases.
A successful outcome
Accura Consulting’s rigorous cost escalation analysis provided the project with a clear understanding of the financial impacts caused by the pandemic. Through data-driven modelling, scenario analysis, and expert validation, the exercise offered actionable insights and robust support for claims resolution, ensuring financial stability and project continuity amid challenging conditions.
Back to News and Insights