Tackling Non-Cladding Building Defects: The value of construction quantum experts

Accura Forensic Quantum Expert cladding defects

The recent Non-Cladding Building Defects report by Cladding Safety Victoria underscores the pervasive issues impacting Victorian buildings—ranging from water ingress and black mould to structural deficiencies.

Read the report here > Non-Cladding Building Defects

With nearly 50% of buildings in the Cladding Rectification Program identified as having additional non-cladding defects, the financial burden on property owners has been significant.

On average, rectification costs range from $2,433 to $8,213 per apartment owner, with overall building costs often exceeding $180,000.

In such complex scenarios, construction quantum experts play a crucial role, including:

1. Accurate Valuation of Defects

Construction quantum experts specialise in quantifying the costs of repairing defects, providing a detailed breakdown that ensures all stakeholders—from owners to builders—understand the financial implications. For example, when structural timber decay or water ingress has caused extensive damage, a construction quantum expert can pinpoint not only direct repair costs but also secondary expenses such as mould remediation or temporary accommodations.

2. Unbiased Assessment

In disputes about responsibility for defects—be it poor design, substandard construction, or lack of maintenance—a construction quantum experts provide impartial, evidence-based cost assessments. This ensures fair outcomes, whether negotiating insurance claims, securing strata loans, or resolving legal disputes.

3. Support for Owners and Regulators

Many property owners lack the technical knowledge to assess the scope and cost of building defects. construction quantum experts bridge this gap by providing transparent cost estimates that empower owners' corporations to plan and prioritize repairs effectively. They also assist regulators by quantifying the financial scale of defects across impacted properties, supporting public policy development.

4. Efficiency in Resolution

By valuing defects, the involvement of a construction quantum expert minimizes delays caused by disagreements among stakeholders. A forensic approach ensures that rectification works proceed with clarity and accountability.


A call to action

As the construction industry grapples with the dual challenges of cladding and non-cladding defects, leveraging the expertise of a construction quantum expert can make a difference. Accurate valuations, combined with a collaborative approach, not only help mitigate costs but also restore confidence in the built environment.

For owners, developers, and legal professionals navigating these challenges, a construction quantum expert could be your strongest ally in achieving resolution efficiently and equitably.

Accura Consulting's construction quantum experts are certified and chartered quantity surveyors with extensive experience. They specialize in creating expert reports for insurers, legal disputes, and conflict resolution. Importantly, they bring valuable hands-on local experience to every project.



 
 

Related News and
Insights from Accura

Previous
Previous

Tackling Construction Disputes: Forensic Quantity Surveying and Delay Analysis in Action

Next
Next

A Success Story Insight: Preparing a Persuasive, Fact-Based Claim for Cost Escalation