Electrical Substation new builds in Sydney
The New South Wales Power Supply Upgrade Program introduced new Substations and Substation upgrades across the state to generate more robust and reliable power supply.
In the delivery of two Substation new builds, the Design and Construct JV experienced latent conditions that impacted the project.
Featured project value: x
Project Date: x
Location: Australia
Service: Claims Consulting, Commercial and Contract Management, Quantum Experts
Industry: Infrastructure
Accura expert: Paul McArd
Leaning on our real-world industry experience, the JV consortium retained experts from Accura Consulting to prosecute an extensive claim relating to the latent conditions.
We conducted a forensic analysis of the historic site records and contract documentation to understand and justify the consortium’s contractual position.
Our experts set out the entitlement in an extensive claim document, producing cost schedules incorporating the costs to be claimed as part of the claim for quantum.
In determining the costs, we reviewed and analysed the project cost ledger, identifying both direct and indirect costs using a robust and justifiable approach.
Working collaboratively, Accura Consulting experts were able to convert one project to a cost reimbursable model following the client’s recognition of the delivery challenges – a great result.
*out of respect for our clients’ privacy, we have opted to omit names from this case study.
Back to Experience