News and Insights
Featured
All articles
Work, site, plant - three definitions you need to know
Construction contracts contain several essential definitions, with three of the most prevalent and occasionally confused being; work, site, and plant.
What is disruption in construction and how can it be analysed?
Disruption is an interference that disturbs or slows down a Contractor's usual working methods, leading to reduced efficiency. Disruption is not the same as delay, however a disruption can be the cause of a delay.
How to Build Quantum and Delay Claims and How Global Claims Fit In
When drafting a quantum and/or delay claim based on several events, claimants commonly use inference rather than causation to build their arguments.
Drafting Effective Construction Claims
In the midst of grappling with the intricacies of drafting a construction claim, two pivotal components demand our attention: Global Claims and Contemporaneous Records.
As-Planned vs As-Built Delay Analysis
A simplistic, retrospective methodology, which in its simplest form compares the as-built program to the planned (baseline) program.
Are Invoices Enough?
Increasingly, contractors initial claims assessments are reduced to simply checking invoices received from subcontractors (to prove a cost has been incurred) with negotiation limited to the cost of the rates claimed.
Why Technology is Critical in Keeping Accurate Records
In days gone by, multi-million dollar construction projects relied documents that were entirely handwritten and stored under lock and key. With the continued maturity of technology solutions, all that has changed.
Unveiling the Power of Contract Resets in Construction
A contract reset can serve as a beacon of hope for employers and contractors motivated to find an amicable solution amid significant delays and cost overruns within construction projects.
How Can Flora and Fauna Cause Delays?
Infrastructure, residential, and commercial construction projects can potentially impact natural habitats, affecting flora and fauna.
What to Include in a Good Construction Timeline
To effectively support construction claims, here are key types of data you should record and reference in your timeline.
Claims Timelines and What Makes Them So Important
Maintaining a detailed timeline of events will support an extension of time and cost claim. Here are the main reasons why a timeline is important.
Royal Institution of Chartered Surveyors Dispute Resolution Team of the Year
Accura Consulting is the winner of the RICS Dispute Resolution Team of the Year for 2022.
Top Issues Faced by Tunnelling Projects
Tunnelling projects are complicated, and all parties — the customer, EPC contractors and subcontractors — expect the work to be done on-time and on budget but delays and cost overruns happen.
Delay Analysis Under the NEC Contract
The NEC contract prescribes that an extension of time, delay and quantum be determined prospectively. The NEC contract requires the contractor to maintain an up-to-date program.
Pricing of Construction Work when Providing an Independent Quantum Assessment
Whether it be assessing insurance claims, variation claims, or the remediation of defective works, a quantum expert is called upon to provide an independent subjective opinion to assist an insurer or a tribunal or, in some cases, to help parties settle a matter outside of formal proceedings.
The Contract Program and Demonstrating Delay
The term “Contract Program” is often used in reference to the Construction or Contractor’s Program. The Construction (or Contractor’s) Program is basically the execution plan and timeline of how the works under the Contract will be carried out and measured. It should consider the key sequences of work and resource dependencies. It should also, depending on the Contract, identify the critical path and the relationships between the planned activities and interfaces.
What Type of Delay Analysis is Required Under the Contract?
This article considers the contractual requirements regarding the most appropriate and accepted method of delay analysis in the commonly used Australian Standard General Conditions of Contract.
Four Delay Analysis Methodologies You Need to Know
A lot has already been written about various delay analysis methodologies. The purpose of this article is to summarise the pros and cons of the most commonly accepted methodologies and highlight where they might best be used.
Mitigation, Acceleration and Constructive Acceleration
In this article we are going to consider the differences between mitigation, acceleration, and constructive acceleration. The recent case of V601 v Probuild[1] is of interest, as it demonstrates that a constructive acceleration claim can be successful in certain circumstances.
The Importance of Contemporaneous Records
Project teams are often told to keep daily or even hourly records of events that occur on-site if a claim for additional time and cost arises. These records are known as contemporaneous records in that they are ‘recorded’ when the event occurs.
Never miss an update
Sign up with your email address to receive news and updates.
Accura Consulting is purposefully lean and independently owned.
We are forensic quantum and delay experts not bound by restrictions and bureaucracy, enabling us to easily adapt to rapidly changing landscapes and provide a tailored approach effective to the situation.
We are committed to establishing and nurturing long-term client relationships built on respect, trust and excellence.
Our Vision is to help our clients make confident decisions. We are there to provide guidance and help clients gain a better understanding of the process and situations they find themselves in. That’s why our news and insights features an array of learning articles to help you find the answers to problems you may encounter.