Experience
Featured
All case studies
Wind Farm in New Zealand | Snapshot
Accura Consulting experts provide clients with a tailored approach to their problems, relying on a fact-based approach to analyse delays with impartiality.
Victorian Solar Farm Project
One of the challenges found in many renewables projects relates to connections and grid issues. For one major wind project in Victoria, this was the case for the EPC.
Metro City Road Tunnel, Australia | Snapshot
Accura Consulting was employed by a major Employer following delays to a significant metro city road tunnel with a value of $5bn.
Sydney Arterial Road Project, Australia | Snapshot
Engaged by a major Tier 1 Contractor on a construct only road project, Accura Consulting supported the Contractor in preparing both quantum and delay claims, translating a complex set of delays into clear, easy to understand analysis.
Road and Bridge Project, Australia | Snapshot
Accura Consulting was engaged by an international Tier 1 Contractor following delays to a road and bridge design and construction project in Australia.
Education Facility, Australia | Snapshot
Accura Consulting’s delay experts were engaged following a delay in the construction and refurbishment of an education facility located in Australia.
Road Tunnel Delay | Snapshot
2020 and 2021 were challenging years for the construction industry. Accura Consulting experts were engaged to support a significant road tunnel project faced with delays and cost overruns relating to COVID-19.
Dubai Shopping Mall | Snapshot
Shopping malls are a major attraction in Dubai and disputes arising there need to be handled quickly and efficiently.
Pacific Highway Upgrade Project in northern New South Wales
A major highway upgrade project to introduce 20 kilometre of dual carriageway including bridges over rivers and flood plains, completed in mid-2018.
Major Regeneration Project Development in Sydney
The Project was a major redevelopment along the Sydney foreshore which includes a mix of commercial and residential buildings, an entertainment precinct, harbour walk and public parkland.
140ML Wastewater Treatment Plant Upgrade
The project involved the design and construction of a new sewage treatment facility with a hydraulic capacity of 140ML/day.
Woolgooga to Ballina Road and Bridge Pacific Highway
The Woolgoolga to Ballina Pacific Highway upgrade was the final link in the Pacific Highway upgrade, between Hexham and Queensland border to be upgraded to four lanes, divided carriageway
Vietnam Offshore Wind Farm - Delay and Variations
The growth of renewables projects in Vietnam resulted in the commencement of a major offshore wind project which engaged a known EPC the lead design and construction.
Major Wind EPC Runs into Delays
Many wind projects engage an EPC to lead the manufacturing, design, development, engineering and procurement of a project. Due to legislation, environmental factors, and shortage of skilled labour, projects often experience delays.
Rail Tunnel for a Tier 1 Contractor
Improvements to rail access to a major city centre had been under consideration for almost a century before the Rail project commenced, linking one side of the CBD to the other via underground stations and a new station to connect to the existing Line.
Oil Refinery
Accura Consulting was engaged to support a Kuwaiti employer following delays in its oil refinery construction projects.
Renewable Wind Energy Project
Renewable wind energy construction projects are part of a rapidly expanding renewables industry however due to legislation, environmental factors, and inexperience, often experience delays.
Major Road Tunnel
At the start of 2020, Australia’s vital government transport infrastructure construction projects were in full flow. As cities continued to sprawl and road traffic increased, tunnels provided a critical way of linking different parts of cities without impacting residential areas.
Never miss an update
Sign up with your email address to receive news and updates.